HPC Ellendale 100 MW facility groundbreaking
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Applied Digital broke ground on a 100 MW HPC data center project in Ellendale, ND on land adjacent to its existing 180 MW data center hosting facility.
Source (primary)
Applied Digital S-1/A filed 2024-11-22 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We also broke ground on a 100 MW HPC data center project in Ellendale, ND (the "HPC Ellendale Facility"), on land located adjacent to its existing 180 MW Data center hosting facility.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital S-1/A filed 2024-11-22
Quote: “We also broke ground on a 100 MW HPC data center project in Ellendale, ND (the "HPC Ellendale Facility"), on land located adjacent to its existing 180 MW Data center hosting facility.”