Polaris Forge 1 Building 2 phase 2 Ready for Service
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
The second phase of Building 2 at Polaris Forge 1 in Ellendale, ND reached Ready for Service, adding 75 MW of critical IT load across three 25 MW halls, completing Building 2's 150 MW and bringing the campus's fully operational critical IT load to 250 MW.
Source (primary)
Why Applied Digital (APLD) Stock Is Trading Up Today - Yahoo Finance (-, news_article)
View cached copy (2026-10-07)Live source ↗Archive.org ↗
Quote: “the addition brings 75 MW of critical IT load across three 25 MW halls, completing Building 2's 150 MW and lifting the campus's fully operational critical IT load to 250 MW”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The article, citing the company press release, reports every element: the Ready for Service milestone, 75 MW across three 25 MW halls, completion of Building 2's 150 MW, and 250 MW operational campus-wide.
Confirmed in the source:
- The second phase of Building 2 at Applied Digital's Polaris Forge 1 campus in Ellendale, North Dakota reached Ready for Service
- The addition brings 75 MW of critical IT load across three 25 MW halls
- The addition completes Building 2's 150 MW
- The campus's fully operational critical IT load rose to 250 MW
What we did: Read our cached copy of the publisher (https://finance.yahoo.com/markets/stocks/articles/why-applied-digital-apld-stock-193634841.html) in full (9,971 characters, retrieved October 7, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Why Applied Digital (APLD) Stock Is Trading Up Today - Yahoo Finance
Quote: “the addition brings 75 MW of critical IT load across three 25 MW halls, completing Building 2's 150 MW and lifting the campus's fully operational critical IT load to 250 MW”
confirms applied-digital 8-K exhibit (apldq127earningsrelease.htm)
Quote: “On October 1, 2026, the Company achieved Ready for Service for the second 75 MW phase of Building 2 at Polaris Forge 1, bringing fully operational critical IT load at the campus to 250 MW across two buildings and 10 data halls”