Polaris Forge 1 Building 2 phase 2 Ready for Service

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility capacity
Statement date
2026-10-06
Promised amount
250.0 MW
Current status
stated

The claim, verbatim

The second phase of Building 2 at Polaris Forge 1 in Ellendale, ND reached Ready for Service, adding 75 MW of critical IT load across three 25 MW halls, completing Building 2's 150 MW and bringing the campus's fully operational critical IT load to 250 MW.

Source (primary)

Why Applied Digital (APLD) Stock Is Trading Up Today - Yahoo Finance (-, news_article)
View cached copy (2026-10-07)Live source ↗Archive.org ↗

Quote: “the addition brings 75 MW of critical IT load across three 25 MW halls, completing Building 2's 150 MW and lifting the campus's fully operational critical IT load to 250 MW”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The article, citing the company press release, reports every element: the Ready for Service milestone, 75 MW across three 25 MW halls, completion of Building 2's 150 MW, and 250 MW operational campus-wide.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://finance.yahoo.com/markets/stocks/articles/why-applied-digital-apld-stock-193634841.html) in full (9,971 characters, retrieved October 7, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Why Applied Digital (APLD) Stock Is Trading Up Today - Yahoo Finance

Quote: “the addition brings 75 MW of critical IT load across three 25 MW halls, completing Building 2's 150 MW and lifting the campus's fully operational critical IT load to 250 MW”

View cached copy (2026-10-07)Live source ↗Archive.org ↗

confirms applied-digital 8-K exhibit (apldq127earningsrelease.htm)

Quote: “On October 1, 2026, the Company achieved Ready for Service for the second 75 MW phase of Building 2 at Polaris Forge 1, bringing fully operational critical IT load at the campus to 250 MW across two buildings and 10 data halls”

View cached copy (2026-10-08)Live source ↗