Ellendale HPC facility ready for service

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-04-14
Promised by
2025-12-31
Current status
verified

What the later record shows

Delivered on time · happened October 31, 2025

The company reported ready-for-service at Polaris Forge 1's first building on schedule. Filings date operation to October 2025, inside the promised second half of 2025.

“delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”
2026-01-06 · applied-digital 8-K exhibit (apldq226earningsrelease.htm) View cached copy (2026-09-22)Live source ↗
“Our first HPC data center at the campus, with approximately 100 MW of critical IT load, became operational in October 2025.”
2026-07-29 · View 10-K View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Building will be ready for service in the second half of 2025, with construction remaining on schedule

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The April 14, 2025 release says construction remains on schedule and the building will be ready for service in the second half of this calendar year, which is 2025.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/121/applied-digital-reports-fiscal-third-quarter-2025-results/) in full (33,113 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms View 10-K

Quote: “Our first HPC data center at the campus, with approximately 100 MW of critical IT load, became operational in October 2025.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)

Quote: “delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”

View cached copy (2026-09-22)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-04-14.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.