Ellendale HPC facility ready for service
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Delivered on time · happened October 31, 2025
The company reported ready-for-service at Polaris Forge 1's first building on schedule. Filings date operation to October 2025, inside the promised second half of 2025.
“delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”
2026-01-06 · applied-digital 8-K exhibit (apldq226earningsrelease.htm) View cached copy (2026-09-22)Live source ↗
“Our first HPC data center at the campus, with approximately 100 MW of critical IT load, became operational in October 2025.”
2026-07-29 · View 10-K View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Building will be ready for service in the second half of 2025, with construction remaining on schedule
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The April 14, 2025 release says construction remains on schedule and the building will be ready for service in the second half of this calendar year, which is 2025.
Confirmed in the source:
- Construction of the Ellendale HPC building remains on schedule
- The building will be ready for service in the second half of calendar year 2025 (the release, dated April 14, 2025, says 'second half of this calendar year')
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/121/applied-digital-reports-fiscal-third-quarter-2025-results/) in full (33,113 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”
confirms View 10-K
Quote: “Our first HPC data center at the campus, with approximately 100 MW of critical IT load, became operational in October 2025.”
confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)
Quote: “delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”