Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Live capacity at Polaris Forge 1 reached 250 MW.
Source (primary)
Applied Digital Q1 Earnings Miss on Higher Costs, Revenues Beat - Yahoo Finance (-, news_article)
View cached copy (2026-10-09)Live source ↗
Quote: “taking live capacity to 250 MW”
How we checked this
Checked on October 14, 2026. The cited source supports every part of this claim.
The article says the second 75 MW phase at the campus became ready on Oct. 1, taking live capacity to 250 MW.
Confirmed in the source:
- Live capacity at Polaris Forge 1 reached 250 MW after a second 75 MW phase became ready on Oct. 1
What we did: Read our cached copy of the publisher (https://finance.yahoo.com/markets/stocks/articles/applied-digital-q1-earnings-miss-140100245.html) in full (12,813 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital Q1 Earnings Miss on Higher Costs, Revenues Beat - Yahoo Finance
Quote: “taking live capacity to 250 MW”