Polaris Forge 1 second 150MW facility online
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Partly delivered
By July 2026 only Phase 1 (75 MW) of Building 2 at Polaris Forge 1 had reached Ready for Service, bringing the campus to 175 MW (100 MW plus 75 MW). That leaves the rest of the second 150 MW facility still pending. The passages do not explicitly name Building 2 as the 150 MW facility, so the link is inferred from the capacity figures.
“our 1,200 skilled craft professionals are continuing to advance the next two 150 MW facilities in parallel.”
2026-04-08 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“Achieved Ready for Service for Phase 1 of Building 2 (75 MW) at Polaris Forge 1 on schedule, bringing total live capacity at the campus to 175 MW.”
2026-07-27 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
A second 150MW facility at Polaris Forge 1 is under construction and scheduled to come online in mid-2026.
Source (primary)
applied-digital 8-K exhibit (apldq425earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-09)Live source ↗
Quote: “a second 150 MW facility scheduled to come online in mid-2026”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The release says construction is underway on a second 150MW data center at the campus, scheduled to come online in mid-2026.
Confirmed in the source:
- A second 150MW facility is planned at Polaris Forge 1
- Construction is already underway on the second facility
- It is scheduled to come online in mid-2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487925000019/apldq425earningsrelease.htm) in full (40,651 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms applied-digital 8-K exhibit (apldq425earningsrelease.htm)
Quote: “a second 150 MW facility scheduled to come online in mid-2026”