Polaris Forge 1 first 100 MW building operational Q4 2025
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Delivered on time · happened October 31, 2025
The first 100 MW building became operational in October 2025, within Q4 2025. The company reported reaching ready-for-service on schedule.
“delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”
2026-01-06 · applied-digital 8-K exhibit (apldq226earningsrelease.htm) View cached copy (2026-09-22)Live source ↗
“The first 100 MW building at Polaris Forge 1 became operational in October 2025.”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The first 100 MW building at Polaris Forge 1 is nearing completion, on time and on budget. It is on track to be operational in calendar Q4 2025, and tenant fit-out for CoreWeave has begun.
Source (primary)
applied-digital 8-K exhibit (apldq126earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-29)Live source ↗
Quote: “Our first 100 MW facility at Polaris Forge 1 remains on track to be operational in calendar Q4 2025”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release says the 100 MW building is nearing completion, on time and on budget, with CoreWeave tenant fit-out started, and on track to be operational in calendar Q4 2025.
Confirmed in the source:
- The first 100 MW building at Polaris Forge 1 is nearing completion
- The building remains on time and on budget
- The first 100 MW facility at Polaris Forge 1 is on track to be operational in calendar Q4 2025
- Tenant fit-out for CoreWeave has been initiated
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487925000068/apldq126earningsrelease.htm) in full (33,636 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms applied-digital 8-K exhibit (apldq126earningsrelease.htm)
Quote: “Our first 100 MW facility at Polaris Forge 1 remains on track to be operational in calendar Q4 2025”
confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)
Quote: “delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”
confirms Earnings Release
Quote: “The first 100 MW building at Polaris Forge 1 became operational in October 2025.”