ELN-03 data center capacity
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
ELN-03 has a 150 MW capacity
Source (primary)
Applied Digital 8-K/A filed 2026-04-01 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “the Company's 150 MW data center ("ELN-03")”
How we checked this
Checked on September 15, 2026. The cited source supports every part of this claim.
The filing describes ELN-03 as the Company's 150 MW data center.
Confirmed in the source:
- ELN-03 is a 150 MW data center
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315226014498/form8-ka.htm) in full (11,503 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 8-K/A filed 2026-04-01
Quote: “the Company's 150 MW data center ("ELN-03")”