Polaris Forge 1 Building 2 Phase 1 RFS
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Not a promise: a reported event · happened July 1, 2026
The claim restates a Phase 1 Ready for Service milestone that occurred on July 1, 2026, as confirmed in the earnings release.
“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW.
Source (primary)
Applied Digital Reports Fiscal First Quarter 2027 Results - Applied Digital Corporation (APLD) (-, news_article)
View cached copy (2026-10-08)Live source ↗Archive.org ↗
Quote: “Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The press release states this delivery, its date, its size, and the resulting 175 MW campus total in its Recent Highlights.
Confirmed in the source:
- Phase 1 of Building 2 at Polaris Forge 1 was 75 MW
- Phase 1 of Building 2 at Polaris Forge 1 was delivered Ready for Service on July 1, 2026
- Total live capacity at the Polaris Forge 1 campus reached 175 MW after that delivery
What we did: Read our cached copy of the publisher (https://ir.applieddigital.com/news-events/press-releases/detail/163/applied-digital-reports-fiscal-first-quarter-2027-results) in full (41,009 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital Reports Fiscal First Quarter 2027 Results - Applied Digital Corporation (APLD)
Quote: “Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW”