Polaris Forge 1 Building 2 Phase 1 (75 MW) delivered June 30, 2026
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Not a promise: a reported event · happened July 1, 2026
The claim reports a delivery that had already happened, giving the date as June 30, 2026. Later company filings and news date Phase 1 Ready for Service to July 1, 2026.
“Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW.”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 on June 30, 2026 on schedule.
Source (primary)
EX-99.1 (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗
Quote: “the Company delivered Phase 1 of Building 2 (75 MW) on June 30, 2026, bringing the total live capacity at the campus to 175 MW.”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The HPC Hosting Update gives the June 30, 2026 date, and the Subsequent to the Quarter section says Ready for Service was achieved on schedule.
Confirmed in the source:
- Applied Digital delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 on June 30, 2026
- The delivery was on schedule
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/sec-filings/all-sec-filings/content/0001144879-26-000044/apldq426earningsreleaseasf.htm) in full (54,584 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms EX-99.1
Quote: “the Company delivered Phase 1 of Building 2 (75 MW) on June 30, 2026, bringing the total live capacity at the campus to 175 MW.”