jain.com

CoreWeave Building 4 150 MW lease at Polaris Forge 1

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
customer
Statement date
2026-07-29
Promised amount
150.0 MW
Current status
stated

The claim, verbatim

Entered into third lease with CoreWeave for additional 150 MW, total contracted capacity at Polaris Forge 1 400 MW

Source (primary)

View 10-K (IR page (ir.applieddigital.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “APLD ELN-02 C LLC entered into a third lease (the 'Building 4 Lease') with CoreWeave for an additional 150 MW, bringing the total contracted capacity at Polaris Forge 1 under our CoreWeave leases to 400 MW”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 10-K describes the August 28, 2025 Building 4 Lease with CoreWeave for an additional 150 MW, bringing total contracted capacity at Polaris Forge 1 to 400 MW.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/sec-filings/all-sec-filings/content/0001144879-26-000048/0001144879-26-000048.pdf) in full (630,756 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms View 10-K

Quote: “APLD ELN-02 C LLC entered into a third lease (the 'Building 4 Lease') with CoreWeave for an additional 150 MW, bringing the total contracted capacity at Polaris Forge 1 under our CoreWeave leases to 400 MW”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2026-07-29.