Polaris Forge 1 Building 2 Phase 1 Ready for Service

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2026-07-27
Promised amount
175.0 MW
Event date
2026-07-01
Current status
stated

What the later record shows

Not a promise: a reported event · happened July 1, 2026

The claim reports a delivery that had already happened. The company's later releases date Phase 1 Ready for Service to July 1, 2026, not June 30, and confirm that the first 100 MW building became operational in October 2025.

“Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW.”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The first 100 MW building at Polaris Forge 1 became operational in October 2025.”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 on schedule on June 30, 2026, bringing total live capacity at the campus to 175 MW; the first 100 MW data center became operational in October 2025.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “the Company delivered Phase 1 of Building 2 (75 MW) on June 30, 2026, bringing the total live capacity at the campus to 175 MW”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release states the June 30, 2026 delivery date, says it was on schedule, gives the 175 MW total, and dates the first 100 MW to October 2025.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/159/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (55,619 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “the Company delivered Phase 1 of Building 2 (75 MW) on June 30, 2026, bringing the total live capacity at the campus to 175 MW”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “the Company delivered Phase 1 of Building 2 (75 MW) on June 30, 2026, bringing the total live capacity at the campus to 175 MW”

View cached copy (2026-10-03)Live source ↗

confirms Earnings Release

Quote: “the Company delivered Phase 1 of Building 2 (75 MW) on June 30, 2026, bringing the total live capacity at the campus to 175 MW”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “the Company delivered Phase 1 of Building 2 (75 MW) on June 30, 2026, bringing the total live capacity at the campus to 175 MW”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 30, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2026-07-27.