Promised amount
400.0 MW
Current status
stated

The claim, verbatim

Polaris Forge 1 data center campus planned for 400 MW total capacity

Source (primary)

ARS (IR page (ir.applieddigital.com), ir_release)
View cached copy (2026-09-01)Live source ↗

Quote: “our ability to complete construction of the first 100 MW HPC facility of our 400 MW Ellendale, North Dakota data center campus ("Polaris Forge 1")”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 10-K calls Polaris Forge 1 a 400 MW campus, which matches its stated plan of 100 MW, 150 MW and 150 MW buildings.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/sec-filings/all-sec-filings/content/0001493152-25-014502/formars.pdf) in full (529,223 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms ARS

Quote: “our ability to complete construction of the first 100 MW HPC facility of our 400 MW Ellendale, North Dakota data center campus ("Polaris Forge 1")”

View cached copy (2026-09-01)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-09-20.