jain.com

Polaris Forge 1 reaches 250 MW operational

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility capacity
Statement date
2026-10-07
Promised amount
250.0 MW
Current status
verified

The claim, verbatim

Polaris Forge 1 reached 250 MW of operational capacity after another 75 MW came online on October 2.

Source (primary)

Applied Digital to Report First-Quarter Earnings: Will APLD Stock Break $20 or Rebound Off Support? - FXLeaders (-, news_article)
View cached copy (2026-10-09)Live source ↗Archive.org ↗

Quote: “Polaris Forge 1 has now reached 250 MW of operational capacity following another 75 MW coming online on October 2.”

How we checked this

Checked on October 15, 2026. The cited source supports every part of this claim.

The article states that Polaris Forge 1 has reached 250 MW of operational capacity after another 75 MW came online on October 2, matching every element of the claim.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.fxleaders.com/news/2026/10/07/applied-digital-to-report-first-quarter-earnings-will-apld-stock-break-20-or-rebound-off-support/) in full (29,347 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital to Report First-Quarter Earnings: Will APLD Stock Break $20 or Rebound Off Support? - FXLeaders

Quote: “Polaris Forge 1 has now reached 250 MW of operational capacity following another 75 MW coming online on October 2.”

View cached copy (2026-10-09)Live source ↗Archive.org ↗

confirms Applied Digital Ends the Quarter With $36 Billion in Contracted Revenue as AI Moat Widens - Yahoo Finance

Quote: “Both are now fully operational. Together, they hold 10 data halls and 250 megawatts of critical IT load”

View cached copy (2026-10-12)Live source ↗Archive.org ↗

confirms Applied Digital Reports Today: What to Know - TradingView

Quote: “Polaris Forge 1 now at 250 MW operational after another 75 MW came online on Oct. 2”

View cached copy (2026-10-14)Live source ↗Archive.org ↗

confirms Applied Digital Stock Earnings Beat And Finland Expansion Signal AI Data Center Momentum - Simply Wall Street

Quote: “the fully leased Polaris Forge 1 campus, which now supports 250 MW of operational critical IT load”

View cached copy (2026-10-14)Live source ↗

Record of changes

October 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 14, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.