Polaris Forge 1 first 100MW building ready Q4 2025

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-08-28
Promised by
2025-12-31
Promised amount
100.0 MW
Current status
verified

What the later record shows

Delivered on time · happened October 31, 2025

The company reported achieving Ready-for-Service on the first 100 MW building for CoreWeave on schedule. Later releases date this to October 2025, within Q4 2025.

“Achieved Ready‑for‑Service at Polaris Forge 1, delivering 100 MW on schedule and fully energizing the first building (ELN-02)”
2026-01-06 · applied-digital 8-K exhibit (apldq226earningsrelease.htm) View cached copy (2026-09-22)Live source ↗
“The first 100 MW building at Polaris Forge 1 became operational in October 2025.”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The first 100MW data center for CoreWeave is scheduled to be ready for service in Q4 2025.

Source (primary)

applied-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-04)Live source ↗

Quote: “the first 100MW data center for CoreWeave is scheduled to be ready for service in Q4 of 2025”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

Applied Digital's Aug. 29, 2025 press release states the first 100MW data center for CoreWeave is scheduled to be ready for service in Q4 of 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000149315225012458/ex99-1.htm) in full (7,542 characters, retrieved October 4, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (ex99-1.htm)

Quote: “the first 100MW data center for CoreWeave is scheduled to be ready for service in Q4 of 2025”

View cached copy (2026-10-04)Live source ↗

confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)

Quote: “Achieved Ready‑for‑Service at Polaris Forge 1, delivering 100 MW on schedule and fully energizing the first building (ELN-02)”

View cached copy (2026-09-22)Live source ↗

confirms Earnings Release

Quote: “The first 100 MW building at Polaris Forge 1 became operational in October 2025.”

View cached copy (2026-10-08)Live source ↗

Record of changes

October 4, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 5, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.