Polaris Forge 1 Second 150MW Facility Operational
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Delivered late · happened October 1, 2026
The second 150 MW building (later called Building 2) was delivered in two 75 MW phases, on July 1 and October 1, 2026. Both dates are after the mid-2026 target, although the company described the first phase as on schedule.
“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
“we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”
2026-10-07 · View PDF View cached copy (2026-10-08)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
A second 150 MW HPC facility at Polaris Forge 1 is scheduled to come online in mid-2026
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗
Quote: “a second 150 MW facility scheduled to come online in mid-2026”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release states that a second 150 MW HPC facility at Polaris Forge 1 is scheduled to come online in mid-2026.
Confirmed in the source:
- A second 150 MW facility at Polaris Forge 1 is scheduled to come online in mid-2026
- The facility is part of the company's HPC data center build-out, with construction already underway
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/126/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (41,868 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “a second 150 MW facility scheduled to come online in mid-2026”
confirms View PDF
Quote: “we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”
confirms EX-99.1
Quote: “Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”