Polaris Forge 1 Second 150MW Facility Operational

Company: Applied Digital

Subject kind
facility timeline
Statement date
2026-09-25
Promised by
2026-06-15
Promised amount
150.0 MW
Current status
stated

The claim, verbatim

A second 150 MW HPC facility at Polaris Forge 1 is scheduled to come online in mid-2026

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗

Quote: “a second 150 MW facility scheduled to come online in mid-2026”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “a second 150 MW facility scheduled to come online in mid-2026”

View cached copy (2026-09-25)Live source ↗Archive.org ↗