jain.com

Polaris Forge 1 Second 150MW Facility Operational

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-07-30
Promised by
2026-06-15
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered late · happened October 1, 2026

The second 150 MW building (later called Building 2) was delivered in two 75 MW phases, on July 1 and October 1, 2026. Both dates are after the mid-2026 target, although the company described the first phase as on schedule.

“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
“we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”
2026-10-07 · View PDF View cached copy (2026-10-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

A second 150 MW HPC facility at Polaris Forge 1 is scheduled to come online in mid-2026

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗

Quote: “a second 150 MW facility scheduled to come online in mid-2026”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release states that a second 150 MW HPC facility at Polaris Forge 1 is scheduled to come online in mid-2026.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/126/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (41,868 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “a second 150 MW facility scheduled to come online in mid-2026”

View cached copy (2026-09-25)Live source ↗Archive.org ↗

confirms View PDF

Quote: “we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”

View cached copy (2026-10-08)Live source ↗

confirms EX-99.1

Quote: “Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 25, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 26, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-25 was the source's retrieval date; source published 2025-07-30.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.