Two additional HPC buildings in design phase adding 300 MW at Ellendale

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2024-10-09
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

The company is in the design phase for two additional buildings at Ellendale that will provide 300 MW of additional capacity, increasing total Ellendale capacity to 400 MW.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Furthermore, we are in the design phase for two additional buildings at this location, which will increase the total capacity to 400 MW. Beyond this, we plan to bring an additional 300 MW online through two additional buildings, which are in the design stage, ultimately increasing Ellendale's total HPC capacity to 400 MW.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The release states twice that two additional buildings in design at Ellendale would add 300 MW and bring total capacity there to 400 MW.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/109/applied-digital-reports-fiscal-first-quarter-2025-results/) in full (29,046 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Furthermore, we are in the design phase for two additional buildings at this location, which will increase the total capacity to 400 MW. Beyond this, we plan to bring an additional 300 MW online through two additional buildings, which are in the design stage, ultimately increasing Ellendale's total HPC capacity to 400 MW.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “we are already working on the design of our next two buildings, which will provide an additional 300 MW of capacity at our Ellendale HPC Campus.”

View cached copy (2026-09-25)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2024-10-09.