First Ready-for-Service milestone achieved at Polaris Forge 1

Company: Applied Digital

Subject kind
facility timeline
Statement date
2025-11-11
Current status
stated

The claim, verbatim

Applied Digital recently achieved its first Ready-for-Service milestone for the first data hall at Polaris Forge 1.

Source (primary)

applied-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-26)Live source ↗

Quote: “We recently achieved our first Ready-for-Service milestone for our first data hall at Polaris Forge 1”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms applied-digital 8-K exhibit (ex99-1.htm)

Quote: “We recently achieved our first Ready-for-Service milestone for our first data hall at Polaris Forge 1”

View cached copy (2026-09-26)Live source ↗