Polaris Forge 1 to deliver 400MW to CoreWeave
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Total critical IT capacity across the three CoreWeave long-term leases will be 400MW at Polaris Forge 1.
Source (primary)
applied-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-04)Live source ↗
Quote: “the total critical IT capacity across these three long-term lease agreements will encompass 400MW across Applied Digital’s sprawling, purpose-built Polaris Forge 1 Campus”
How we checked this
Checked on October 6, 2026. The cited source supports every part of this claim.
The release states that total critical IT capacity across the three long-term CoreWeave leases will be 400MW at Polaris Forge 1.
Confirmed in the source:
- There are three long-term lease agreements with CoreWeave at Polaris Forge 1
- Total critical IT capacity across these three leases will be 400MW
- The capacity is at the Polaris Forge 1 Campus
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000149315225012458/ex99-1.htm) in full (7,542 characters, retrieved October 4, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms applied-digital 8-K exhibit (ex99-1.htm)
Quote: “the total critical IT capacity across these three long-term lease agreements will encompass 400MW across Applied Digital’s sprawling, purpose-built Polaris Forge 1 Campus”