Rockdale
Project of Riot
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 700 MW | 2026-08-17 | Rockdale - 700 MW existing power capacity |
| Contracted a customer is on the hook | 241 MW | 2026-08-29 | Total leased data center capacity at Rockdale campus |
| Under construction | 25 MW | 2026-08-10 | Second 25 MW AMD expansion under construction |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 191 MW | 2026-09-01 | Rockdale data center capacity |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2026-01-15
Advanced Micro Devices - tenant · 50 MW · 10-year term source
2026-08-10
Anthropic - tenant · 191 MW · 20-year term source
2026-08-24
Undisclosed counterparty (one or more) - tenant · 20-year term source
Probably Anthropic (14 days apart) our guess
Our inference, not a disclosure. Anthropic announced 191 MW at Rockdale on 2026-08-10, and this site disclosed an unnamed commitment of 191 MW on 2026-08-24 -- the same capacity 14 day(s) apart. The likeliest reading is one deal described twice, so the capacity is counted once and attributed to neither. It could still be a second undisclosed party; if a source names one, this becomes a fact and the capacity returns.
Claims about this project
2025-04-30 - stated
2025-12-30 - stated
Rockdale Facility developed capacity 700.0 MW.
2026-01-15 - stated
2026-03-01 - stated
Rockdale Facility developed capacity 700.0 MW.
2026-03-01 - stated
AMD long-term data center lease 25.0 MW.
2026-03-01 - stated
AMD data center lease at Rockdale 25.0 MW.
2026-03-01 - stated
Rockdale Facility developed capacity 700.0 MW.
2026-03-01 - stated
Rockdale Facility available capacity 700.0 MW.
2026-03-01 - stated
AMD data center lease agreement 25.0 MW.
2026-03-01 - stated
2026-04-29 - stated
AMD Lease expansion option 75.0 MW.
2026-04-29 - stated
2026-04-29 - stated
2026-04-29 - stated
2026-04-29 - stated
AMD Lease right of first refusal 100.0 MW.
2026-05-01 - stated
AMD contracted capacity at Rockdale 50.0 MW.
2026-08-10 - stated
2026-08-10 - stated
2026-08-10 - stated
2026-08-10 - stated
AMD lease expected revenue 311.0 USD.
2026-08-10 - stated
2026-08-10 - stated
Long-term contracted revenue from Anthropic and AMD 9.8 Billion USD.
2026-08-10 - stated
2026-08-10 - stated
2026-08-10 - stated
2026-08-10 - stated
2026-08-10 - stated
2026-08-10 - stated
2026-08-10 - stated
2026-08-10 - stated
Anthropic - $16.1B with extension options 16100.0 M USD.
2026-08-10 - stated
$573M term loan for Anthropic project 573.0 M USD.
2026-08-11 - stated
Anthropic 20-year compute agreement 9000000000.0 USD.
2026-08-12 - stated
Frontier AI lab 20-year lease revenue 9100.0 USD millions.
2026-08-12 - stated
Rockdale full capacity delivery 191.0 MW.
2026-08-12 - stated
Rockdale campus leased capacity 191.0 MW.
2026-08-12 - stated
Rockdale first phase delivery 96.0 MW.
2026-08-12 - stated
2026-08-12 - stated
Total contracted revenue from two AI companies 9800.0 USD millions.
2026-08-12 - stated
2026-08-12 - stated
Total AI company leased capacity 241.0 MW.
2026-08-13 - stated
2026-08-13 - stated
20-year AI lab lease agreement 9.1 USD billions.
2026-08-13 - stated
Term loan on AMD facility cash flows 180.0 USD.
2026-08-13 - stated
Rockdale campus total power capacity 700.0 MW.
2026-08-13 - stated
AMD contracted capacity expansion 50.0 MW.
2026-08-13 - stated
2026-08-13 - stated
2026-08-13 - stated
2026-08-13 - stated
2026-08-13 - stated
2026-08-16 - stated
$9B AI compute deal with Anthropic 9000000000.0 USD.
2026-08-16 - stated
Anthropic AI compute services deal 9100000000.0 USD.
2026-08-16 - stated
AMD compute capacity lease 25.0 MW.
2026-08-16 - stated
Anthropic compute services deal 9.0 USD.
2026-08-16 - stated
Rockdale contracted data-center revenue 9800000000.0 USD.
2026-08-16 - stated
Rockdale facility capacity for Anthropic 191.0 MW.
2026-08-16 - stated
Anthropic AI compute contract 9000000000.0 USD.
2026-08-17 - stated
Rockdale - 241 MW under signed leases 241.0 MW.
2026-08-17 - stated
2026-08-17 - stated
AMD - $1B potential with 200 MW capacity 1000.0 M USD.
2026-08-17 - stated
20-year data centre lease at Rockdale, Texas. Promised by 2048-06-30.
2026-08-17 - stated
2026-08-17 - stated
AMD - 10-year $311M lease (25 MW initial) 311.0 M USD.
2026-08-17 - stated
2026-08-18 - stated
2026-08-18 - stated
Anthropic data center lease agreement 9100000000.0 USD.
2026-08-18 - stated
Anthropic computing capacity lease 191.0 MW.
2026-08-19 - stated
AI lab lease initial contract revenue 9.1 billion USD.
2026-08-19 - stated
Total contracted revenue from Rockdale leases 9.8 billion USD.
2026-08-19 - stated
AI lab lease potential value with extensions 16.1 billion USD.
2026-08-19 - stated
AMD Phase 2 completion 25.0 MW.
2026-08-19 - stated
2026-08-19 - stated
2026-08-19 - stated
2026-08-19 - stated
2026-08-19 - stated
Anthropic data center lease 191.0 MW.
2026-08-19 - stated
2026-08-19 - stated
2026-08-19 - stated
2026-08-20 - stated
20-year colocation agreement duration 20.0 years.
2026-08-20 - stated
Anthropic AI data center partnership 9.1 billion USD.
2026-08-21 - stated
2026-08-21 - stated
Morgan Stanley interim financing facility 573.0 USD.
2026-08-21 - stated
2026-08-21 - stated
2026-08-21 - stated
2026-08-21 - stated
Morgan Stanley interim financing facility 573.0 million USD.
2026-08-21 - stated
Rockdale data center capacity 191.0 MW.
2026-08-21 - stated
2026-08-21 - stated
2026-08-22 - stated
191 MW facility lease for AI customer 191.0 MW.
2026-08-24 - stated
Morgan Stanley delayed-draw facility for Rockdale data center 573000000.0 USD. Promised by 2026-12-31.
2026-08-24 - stated
Rockdale data center capacity delivery schedule. Promised by 2028-06-30.
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
Morgan Stanley facility maturity date. Promised by 2026-12-31.
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-25 - stated
2026-08-25 - stated
Rockdale contracted capacity and revenue 9800000000.0 USD.
2026-08-25 - stated
Long-term contracted revenue from Rockdale capacity 9.8 USD billion.
2026-08-25 - stated
Secured facility for Rockdale data center 573.0 USD.
2026-08-29 - stated
2026-08-29 - stated
2026-08-29 - stated
2026-08-29 - stated
2026-08-31 - stated
$180M term loan from AMD refinancing 180.0 USD.
2026-08-31 - stated
$573M interim facility from Morgan Stanley 573.0 USD.
2026-08-31 - stated
AMD expansion rights at Rockdale 150.0 MW.
2026-08-31 - stated
191MW data center lease 9100.0 USD.
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
Anthropic project capex requirements 2150.0 USD.
2026-09-01 - stated
Rockdale data center capacity 191.0 MW.
2026-09-01 - stated
Rockdale data center capacity 191.0 MW.
2026-09-01 - stated
Rockdale campus 191 MW data center lease 9100000000.0 USD.
2026-09-01 - stated
$573M term loan for Rockdale data center 573.0 USD.
2026-09-01 - stated
Rockdale lease capacity and term 191.0 MW.
2026-09-01 - stated
Rockdale data center term loan 573.0 USD.