jain.com

Initial AI data center deployment at Rockdale

Company: Riot - Project: Rockdale

Subject kind
facility timeline
Statement date
2026-08-19
Promised by
2027-12-31
Promised amount
96.0 MW
Current status
stated

The claim, verbatim

Initial 96 MW deployment expected in December 2027

Source (primary)

Foley Represents Riot Platforms on $9.1B AI Data Center Lease at Rockdale Campus - foley.com (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “the initial 96 IT MW expected in December 2027”

How we checked this

Attempted on September 14, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of the publisher (https://www.foley.com/news/2026/08/foley-represents-riot-platforms-on-9-1b-ai-data-center-lease-at-rockdale-campus/) in full (7,541 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Foley Represents Riot Platforms on $9.1B AI Data Center Lease at Rockdale Campus - foley.com

Quote: “the initial 96 IT MW expected in December 2027”

View cached copy (2026-08-31)Live source ↗