Rockdale Frontier AI Lab RFS1
Company: Riot
The claim, verbatim
The first 96 MW of the Frontier AI Lab deployment at Rockdale is scheduled to be ready for service in December 2027.
Source (primary)
riot 8-K exhibit (riot-ex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-05)Live source ↗
Quote: “DEC 2027 RFS1 96 MW”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms riot 8-K exhibit (riot-ex99d2.htm)
Quote: “DEC 2027 RFS1 96 MW”