Rockdale data center capacity delivery schedule

Company: Riot - Project: Rockdale

Subject kind
facility timeline
Statement date
2026-08-24
Promised by
2028-06-30
Current status
stated

The claim, verbatim

Riot Platforms will deliver the first 96 megawatts of capacity at its Rockdale, Texas data center by December 2027, with the remaining 95 megawatts expected by June 2028.

Source (primary)

Riot Platforms locked in a $9.1 billion Anthropic deal, but its bridge loan expires before the rent starts - CryptoSlate (-, news_article)
View cached copy (2026-09-01)Live source ↗

Quote: “The first 96 MW is scheduled for delivery in December 2027, with the remaining 95 MW expected by June 2028.”

How we checked this

Checked on September 18, 2026. The cited source supports every part of this claim.

The article states that the first 96 MW is scheduled for delivery in December 2027 and the remaining 95 MW is expected by June 2028.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://cryptoslate.com/riot-platforms-locked-in-a-9-1-billion-anthropic-deal-but-its-bridge-loan-expires-before-the-rent-starts/) in full (16,460 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot Platforms locked in a $9.1 billion Anthropic deal, but its bridge loan expires before the rent starts - CryptoSlate

Quote: “The first 96 MW is scheduled for delivery in December 2027, with the remaining 95 MW expected by June 2028.”