jain.com

Rockdale data center capacity delivery schedule

Company: Riot - Project: Rockdale

Subject kind
facility timeline
Statement date
2026-08-24
Promised by
2028-06-30
Current status
stated

The claim, verbatim

Riot Platforms will deliver the first 96 megawatts of capacity at its Rockdale, Texas data center by December 2027, with the remaining 95 megawatts expected by June 2028.

Source (primary)

Riot Platforms locked in a $9.1 billion Anthropic deal, but its bridge loan expires before the rent starts - CryptoSlate (-, news_article)
View cached copy (2026-09-01)Live source ↗

Quote: “The first 96 MW is scheduled for delivery in December 2027, with the remaining 95 MW expected by June 2028.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Riot Platforms locked in a $9.1 billion Anthropic deal, but its bridge loan expires before the rent starts - CryptoSlate

Quote: “The first 96 MW is scheduled for delivery in December 2027, with the remaining 95 MW expected by June 2028.”

View cached copy (2026-09-01)Live source ↗