20-year 191 MW Rockdale lease with frontier AI customer
Company: Riot - Project: Rockdale
The claim, verbatim
In August 2026 Riot announced a 20-year lease for 191 MW of critical IT load at its Rockdale, Texas campus with a leading frontier AI customer.
Source (primary)
Riot Platforms Repays $200 Million Coinbase Credit Facility and Releases Pledged Collateral - Crowdfund Insider (-, news_article)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “In August it announced a 20-year lease for 191 megawatts of critical IT load with a leading frontier AI customer”
How we checked this
Checked on October 1, 2026. The cited source supports part of this claim, but not all of it.
The article confirms the August lease announcement, its 20-year term, its 191 MW size and the frontier AI customer. It does not explicitly tie the lease to the Rockdale campus.
Confirmed in the source:
- In August 2026 Riot announced a 20-year lease for 191 MW of critical IT load
- The lessee is a leading frontier AI customer
- Riot is expanding data-center capacity at its Rockdale, Texas campus
We could not confirm this from the cited source:
- The 191 MW lease is specifically located at Riot's Rockdale, Texas campus
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of the publisher (https://www.crowdfundinsider.com/2026/09/313777-riot-platforms-repays-200-million-coinbase-credit-facility-and-releases-pledged-collateral/) in full (8,277 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Riot Platforms Repays $200 Million Coinbase Credit Facility and Releases Pledged Collateral - Crowdfund Insider
Quote: “In August it announced a 20-year lease for 191 megawatts of critical IT load with a leading frontier AI customer”