Anthropic 191 MW lease at Rockdale, Texas

Company: Riot - Project: Rockdale

Subject kind
partnership
Statement date
2026-08-10
Promised amount
191.0 MW
Current status
stated

The claim, verbatim

20-year lease with Anthropic for 191 megawatts of critical IT capacity at Rockdale, Texas campus

Source (primary)

Riot Platforms Stock Is Up 80% From Its Low. Here’s Where the Stock Could Go in 2026 - TIKR.com (-, news_article)
View cached copy (2026-09-18)Live source ↗

Quote: “On August 10, Riot disclosed a 20-year lease for 191 megawatts of critical IT capacity at its Rockdale, Texas campus with what it called 'one of the world's leading frontier AI labs.' Bloomberg identified the tenant as Anthropic”

How we checked this

Checked on September 24, 2026. The cited source supports part of this claim, but not all of it.

The source confirms the lease's length, size and location. It names Anthropic only through a Bloomberg report and says the larger tenant is 'reportedly' Anthropic, whereas the claim states the counterparty as fact.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of the publisher (https://www.tikr.com/blog/riot-platforms-stock-is-up-80-from-its-low-heres-where-the-stock-could-go-in-2026) in full (13,100 characters, retrieved September 18, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot Platforms Stock Is Up 80% From Its Low. Here’s Where the Stock Could Go in 2026 - TIKR.com

Quote: “On August 10, Riot disclosed a 20-year lease for 191 megawatts of critical IT capacity at its Rockdale, Texas campus with what it called 'one of the world's leading frontier AI labs.' Bloomberg identified the tenant as Anthropic”

View cached copy (2026-09-18)Live source ↗