jain.com

AMD lease at Rockdale

Company: Riot - Project: Rockdale

Subject kind
customer
Statement date
2026-10-08
Promised amount
50.0 MW
Current status
stated

The claim, verbatim

Riot leases capacity to AMD, with 50 megawatts total under the AMD lease, the first 25 MW already leased.

Source (primary)

Riot Platforms’ $573 Million Bridge Loan Comes Due December 31 as Shares Fall 8% in October’s First Week. Time to Sell or Load Up? - TIKR.com (-, news_article)
View cached copy (2026-10-10)Live source ↗Archive.org ↗

Quote: “financing against the first 25 megawatts leased to AMD (AMD)”

How we checked this

Checked on October 14, 2026. The cited source supports every part of this claim.

The article refers to the first 25 megawatts leased to AMD and to AMD's 50 megawatts being fully delivered by May 2027.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.tikr.com/blog/riot-platforms-573-million-bridge-loan-comes-due-december-31-as-shares-fall-8-in-octobers-first-week-time-to-sell-or-load-up) in full (10,000 characters, retrieved October 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot Platforms’ $573 Million Bridge Loan Comes Due December 31 as Shares Fall 8% in October’s First Week. Time to Sell or Load Up? - TIKR.com

Quote: “financing against the first 25 megawatts leased to AMD (AMD)”

View cached copy (2026-10-10)Live source ↗Archive.org ↗