Rockdale Building G online Q4 2023

Company: Riot - Project: Rockdale

Subject kind
facility timeline
Statement date
2023-09-05
Promised by
2023-12-31
Promised amount
100.0 MW
Current status
verified

What the later record shows

Delivered on time

A December 5, 2023 presentation states that both 100 MW immersion-cooled self-mining buildings at Rockdale were completed, which was within Q4 2023. Building G is not named explicitly.

“buildings (200 MW) for self-mining at the Rockdale Facility have been completed”
2023-12-05 · riot 8-K exhibit (riot-20231204xex99d2.htm) View cached copy (2026-11-15)Live source ↗

Checked November 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Rockdale Building G, a 100 MW immersion-cooled self-mining building, has a start date of Q4 2023.

Source (primary)

riot 8-K exhibit (riot-20230906xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-20)Live source ↗

Quote: “G Q4 2023 100 MW Immersion-cooled Self-mining”

How we checked this

Checked on November 21, 2026. The cited source supports every part of this claim.

The Rockdale appendix table lists Building G with a Q4 2023 start date, 100 MW, immersion-cooled, self-mining.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000155837023015517/riot-20230906xex99d2.htm) in full (31,186 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms riot 8-K exhibit (riot-20230906xex99d2.htm)

Quote: “G Q4 2023 100 MW Immersion-cooled Self-mining”

View cached copy (2026-11-20)Live source ↗

confirms riot 8-K exhibit (riot-20231204xex99d2.htm)

Quote: “buildings (200 MW) for self-mining at the Rockdale Facility have been completed”

View cached copy (2026-11-15)Live source ↗

Record of changes

November 20, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 20, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.