jain.com

Rockdale frontier AI lab first delivery

Company: Riot - Project: Rockdale

Subject kind
facility timeline
Statement date
2026-11-04
Promised by
2027-12-31
Current status
stated

The claim, verbatim

The first delivery under the 191 MW Rockdale Tier 3 lease with the frontier AI lab is scheduled for December 2027.

Source (primary)

[Riot Platforms Q3 2026 Earnings Call] Riot Signs Largest-Ever $28 Billion, 910 MW AI Lease at Corsicana, Targets $2.2 Billion Annual NOI and Says No Equity Needed - finance.biggo.com (-, news_article)
View cached copy (2026-11-05)Live source ↗Archive.org ↗

Quote: “Frontier AI Lab (Rockdale, Tier 3) 191 MW Dec 2027 / Jun 2028”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms [Riot Platforms Q3 2026 Earnings Call] Riot Signs Largest-Ever $28 Billion, 910 MW AI Lease at Corsicana, Targets $2.2 Billion Annual NOI and Says No Equity Needed - finance.biggo.com

Quote: “Frontier AI Lab (Rockdale, Tier 3) 191 MW Dec 2027 / Jun 2028”

View cached copy (2026-11-05)Live source ↗Archive.org ↗