Anthropic data center full 191 MW deployment

Company: Riot - Project: Rockdale

Subject kind
facility capacity
Statement date
2026-08-13
Promised by
2028-06-30
Promised amount
191.0 MW
Current status
stated

The claim, verbatim

Riot Platforms targets full deployment of 191 MW at the Anthropic facility in June 2028.

Source (primary)

Riot Platforms Re-Wires the Ledger for a $9B AI Power Play - MarketBeat (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “followed by full deployment of 191 MW in June 2028”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Riot Platforms Re-Wires the Ledger for a $9B AI Power Play - MarketBeat

Quote: “followed by full deployment of 191 MW in June 2028”

View cached copy (2026-08-31)Live source ↗