Anthropic data center full 191 MW deployment
Company: Riot - Project: Rockdale
The claim, verbatim
Riot Platforms targets full deployment of 191 MW at the Anthropic facility in June 2028.
Source (primary)
Riot Platforms Re-Wires the Ledger for a $9B AI Power Play - MarketBeat (-, news_article)
View cached copy (2026-08-31)Live source ↗
Quote: “followed by full deployment of 191 MW in June 2028”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Riot Platforms Re-Wires the Ledger for a $9B AI Power Play - MarketBeat
Quote: “followed by full deployment of 191 MW in June 2028”
