jain.com

Rockdale site capacity committed to data center lease

Company: Riot

Subject kind
facility capacity
Statement date
2026-10-31
Promised amount
191.0 MW
Current status
stated

The claim, verbatim

Riot committed 191 megawatts at the Rockdale, Texas site to a single long-term data center lease.

Source (primary)

Riot Platforms (RIOT) Following The Rockdale Lease Sell Off Is It A Bargain - Yahoo Finance (-, news_article)
View cached copy (2026-10-31)Live source ↗Archive.org ↗

Quote: “its commitment of 191 megawatts at the Rockdale, Texas site to a single long term data center lease”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Riot Platforms (RIOT) Following The Rockdale Lease Sell Off Is It A Bargain - Yahoo Finance

Quote: “its commitment of 191 megawatts at the Rockdale, Texas site to a single long term data center lease”

View cached copy (2026-10-31)Live source ↗Archive.org ↗