Rockdale Facility developed capacity
Company: Riot - Project: Rockdale
The claim, verbatim
Rockdale Facility has 700 MW of developed capacity available for data center workloads
Source (primary)
Riot 10-K filed 2026-03-02 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “Our large-scale data center located in Rockdale, Texas (the "Rockdale Facility") with 700 megawatts ("MW") of developed capacity available for data center workloads”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Riot 10-K filed 2026-03-02
Quote: “Our large-scale data center located in Rockdale, Texas (the "Rockdale Facility") with 700 megawatts ("MW") of developed capacity available for data center workloads”