AMD data center deployment timeline at Rockdale
Company: Riot - Project: Rockdale
What the later record shows
Delivered on time · happened May 31, 2026
The Q2 2026 10-Q states the first 5 MW was delivered in January 2026 and the remaining 20 MW in May 2026, matching the promised schedule. The press release adds that delivery was on time.
“5 MW of critical IT load capacity that was delivered in January 2026 and the remaining 20 MW that was delivered in May 2026”
2026-08-09 · Riot 10-Q filed 2026-08-10 View cached copy (2026-08-30)Live source ↗
“Riot completed delivery of the final 20 MW of AMD’s initial deployment, bringing the full 25 MW of commissioned capacity online, on time and on budget”
2026-08-09 · riot 8-K exhibit (riot-20260810xex99d1.htm) View cached copy (2026-09-01)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Riot will deliver AMD deployment in two phases: first in January 2026, final completion in May 2026
Source (primary)
riot 8-K exhibit (riot-20260116xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-21)Live source ↗
Quote: “Riot has commenced retrofitting one of its existing buildings, with delivery to AMD expected in two phases: the first in January 2026 and final completion in May 2026.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
Riot's January 16, 2026 press release says delivery to AMD at the Rockdale Site was expected in two phases, the first in January 2026 and final completion in May 2026. The release presents this as an expected schedule, not a firm commitment.
Confirmed in the source:
- Riot is to deliver the AMD deployment at its Rockdale Site in two phases
- The first phase of delivery to AMD was scheduled for January 2026
- Final completion of delivery to AMD was scheduled for May 2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000110465926004551/riot-20260116xex99d1.htm) in full (14,649 characters, retrieved September 21, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20260116xex99d1.htm)
Quote: “Riot has commenced retrofitting one of its existing buildings, with delivery to AMD expected in two phases: the first in January 2026 and final completion in May 2026.”
confirms Riot 10-Q filed 2026-08-10
Quote: “5 MW of critical IT load capacity that was delivered in January 2026 and the remaining 20 MW that was delivered in May 2026”
confirms riot 8-K exhibit (riot-20260810xex99d1.htm)
Quote: “Riot completed delivery of the final 20 MW of AMD’s initial deployment, bringing the full 25 MW of commissioned capacity online, on time and on budget”