jain.com

Rockdale infrastructure tier specification

Company: Riot - Project: Rockdale

Subject kind
facility capacity
Statement date
2026-08-12
Current status
stated

The claim, verbatim

191-megawatt build-to-suit development designed as Tier 3 infrastructure

Source (primary)

Riot Platforms: $16.1 Billion Potential AI Data Center Deal Targets Up To $8.2 Billion Of NOI - Pulse 2.0 (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “The 191-megawatt build-to-suit development is designed as Tier 3 infrastructure.”

How we checked this

Attempted on September 14, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of the publisher (https://pulse2.com/riot-platforms-16-1-billion-potential-ai-data-center-deal-targets-up-to-8-2-billion-of-noi/) in full (2,804 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot Platforms: $16.1 Billion Potential AI Data Center Deal Targets Up To $8.2 Billion Of NOI - Pulse 2.0

Quote: “The 191-megawatt build-to-suit development is designed as Tier 3 infrastructure.”

View cached copy (2026-08-31)Live source ↗