AMD - 50 MW contracted after first expansion

Company: Riot - Project: Rockdale

Subject kind
facility capacity
Statement date
2026-08-17
Promised amount
50.0 MW
Current status
stated

The claim, verbatim

AMD exercised its first 25 MW expansion option in Q1 2026, bringing its contracted capacity to 50 MW

Source (primary)

RIOT stock gains 4.7% as JPMorgan lifts target to $22 - Cryptonews.net (-, news_article)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “AMD exercised its first 25 MW expansion option during the first quarter, bringing its contracted capacity to 50 MW”

How we checked this

Attempted on September 14, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of the publisher (https://cryptonews.net/news/mining/33308679/) in full (8,787 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms RIOT stock gains 4.7% as JPMorgan lifts target to $22 - Cryptonews.net

Quote: “AMD exercised its first 25 MW expansion option during the first quarter, bringing its contracted capacity to 50 MW”