jain.com

AMD data center lease agreement

Company: Riot - Project: Rockdale

Subject kind
customer
Statement date
2026-03-01
Promised amount
25.0 MW
Current status
stated

The claim, verbatim

Long-term data center lease agreement with AMD to provide initially 25 MW of critical IT load capacity at Rockdale Facility with a 10-year initial term, expansion options for up to 75 additional MW, and right of first refusal for up to 100 additional MW

Source (primary)

Riot 10-K filed 2026-03-02 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “execution of a long-term data center lease agreement (the "AMD Lease") with Advanced Micro Devices, Inc. ("AMD"), to initially provide 25 MW of critical IT load capacity at the Rockdale Facility. The AMD Lease has an initial term of ten years and provides for expansion options for up to an additional 75 MW of critical IT load capacity, and a right of first refusal of up to an additional 100 MW”

How we checked this

Checked on September 16, 2026. The cited source supports every part of this claim.

Every term in the claim — counterparty, site, 25 MW initial capacity, ten-year initial term, 75 MW expansion option and 100 MW right of first refusal — appears in the filing.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000110465926022322/riot-20251231x10k.htm) in full (516,452 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot 10-K filed 2026-03-02

Quote: “execution of a long-term data center lease agreement (the "AMD Lease") with Advanced Micro Devices, Inc. ("AMD"), to initially provide 25 MW of critical IT load capacity at the Rockdale Facility. The AMD Lease has an initial term of ten years and provides for expansion options for up to an additional 75 MW of critical IT load capacity, and a right of first refusal of up to an additional 100 MW”

View cached copy (2026-08-31)Live source ↗