AMD data center lease at Rockdale (50 MW)
Company: Riot - Project: Rockdale
The claim, verbatim
AMD has 50 megawatts of data center capacity under contract at Rockdale
Source (primary)
Riot Platforms Just Signed a $9.1 Billion AI Lease Reportedly With Anthropic, and Shares Jumped 25% - FinanceFeeds (-, news_article)
View cached copy (2026-09-02)Live source ↗Archive.org ↗
Quote: “AMD now has 50 megawatts under contract”
How we checked this
Checked on September 16, 2026. The cited source supports every part of this claim.
The article states directly that AMD now has 50 megawatts under contract at Rockdale.
Confirmed in the source:
- AMD has 50 megawatts of data-center capacity under contract at Riot's Rockdale site
- Riot began converting Rockdale's power capacity for data-center tenants with a lease to AMD
What we did: Read our cached copy of the publisher (https://financefeeds.com/riot-platforms-just-signed-a-9-1-billion-ai-lease-reportedly-with-anthropic-and-shares-jumped-25/) in full (12,592 characters, retrieved September 2, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Riot Platforms Just Signed a $9.1 Billion AI Lease Reportedly With Anthropic, and Shares Jumped 25% - FinanceFeeds
Quote: “AMD now has 50 megawatts under contract”