700 MW total Whinstone Facility capacity after 400 MW expansion including 200 MW immersion-cooled
Company: Riot - Project: Rockdale
The claim, verbatim
Announced large-scale expansion of Whinstone Facility by 400 MW (including 200 MW immersion-cooled infrastructure) anticipated to bring total capacity to 700 MW
Source (primary)
Riot 10-K filed 2022-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “we announced a large-scale expansion of the Whinstone Facility by 400 MW, including 200 MW of immersion-cooled Bitcoin mining infrastructure, which is anticipated to bring the Whinstone Facility to 700 MW in total capacity of Bitcoin mining infrastructure”
How we checked this
Checked on September 22, 2026. The cited source supports every part of this claim.
The document confirms the 400 MW expansion (including 200 MW immersion-cooled) anticipated to bring Whinstone to 700 MW.
Confirmed in the source:
- Riot announced a large-scale expansion of the Whinstone Facility by 400 MW
- The expansion includes 200 MW of immersion-cooled infrastructure
- The expansion is anticipated to bring total capacity to 700 MW
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000107997322000280/riot10k1221.htm) in full (467,403 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Riot 10-K filed 2022-03-16
Quote: “we announced a large-scale expansion of the Whinstone Facility by 400 MW, including 200 MW of immersion-cooled Bitcoin mining infrastructure, which is anticipated to bring the Whinstone Facility to 700 MW in total capacity of Bitcoin mining infrastructure”
