700 MW total Whinstone Facility capacity after 400 MW expansion including 200 MW immersion-cooled
Company: Riot - Project: Rockdale
The claim, verbatim
Announced large-scale expansion of Whinstone Facility by 400 MW (including 200 MW immersion-cooled infrastructure) anticipated to bring total capacity to 700 MW
Source (primary)
Riot 10-K filed 2022-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “we announced a large-scale expansion of the Whinstone Facility by 400 MW, including 200 MW of immersion-cooled Bitcoin mining infrastructure, which is anticipated to bring the Whinstone Facility to 700 MW in total capacity of Bitcoin mining infrastructure”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Riot 10-K filed 2022-03-16
Quote: “we announced a large-scale expansion of the Whinstone Facility by 400 MW, including 200 MW of immersion-cooled Bitcoin mining infrastructure, which is anticipated to bring the Whinstone Facility to 700 MW in total capacity of Bitcoin mining infrastructure”