Rockdale project financing commitment

Company: Riot - Project: Rockdale

Subject kind
financing
Statement date
2026-09-17
Promised amount
573.0 million USD
Current status
stated

The claim, verbatim

Lending group committed up to $573 million in delayed-draw term financing for Rockdale 191 megawatt project

Source (primary)

Riot Platforms rises as AI data center narrative stays in focus - Quiver Quantitative (-, news_article)
View cached copy (2026-09-20)Live source ↗

Quote: “a lending group committed up to $573 million in delayed-draw term financing to support long-lead equipment and other costs tied to the Rockdale 191 megawatt project”

How we checked this

Checked on September 25, 2026. The cited source supports every part of this claim.

The article reports that an August filing showed a lending group committing up to $573 million in delayed-draw term financing for costs tied to the Rockdale 191 megawatt project.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.quiverquant.com/news/Riot+Platforms+rises+as+AI+data+center+narrative+stays+in+focus) in full (8,298 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot Platforms rises as AI data center narrative stays in focus - Quiver Quantitative

Quote: “a lending group committed up to $573 million in delayed-draw term financing to support long-lead equipment and other costs tied to the Rockdale 191 megawatt project”

View cached copy (2026-09-20)Live source ↗