AMD Phase 2 completion

Company: Riot - Project: Rockdale

Subject kind
facility capacity
Statement date
2026-08-19
Promised amount
25.0 MW
Current status
stated

The claim, verbatim

Phase 2 of AMD lease (20 megawatts) delivered in May, bringing total AMD capacity to 25 megawatts

Source (primary)

JPMorgan Boosts Riot Platforms Price Target to $22 on Digital Infrastructure Strength - TIKR.com (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “Phase 2 of that lease, 20 megawatts of IT capacity, was delivered in May, bringing total AMD capacity online to 25 megawatts”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms JPMorgan Boosts Riot Platforms Price Target to $22 on Digital Infrastructure Strength - TIKR.com

Quote: “Phase 2 of that lease, 20 megawatts of IT capacity, was delivered in May, bringing total AMD capacity online to 25 megawatts”

View cached copy (2026-08-31)Live source ↗