Rockdale Facility Hash Rate Expansion

Company: Riot - Project: Rockdale

This claim was marked delayed on September 14, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2024-02-26
Promised by
2024-07-31
Promised amount
15.1 EH/s
Current status
delayed

The claim, verbatim

Riot anticipates the Rockdale Facility's total hash rate capacity will increase from 12.4 EH/s to 15.1 EH/s by end of July 2024 upon deployment of the new M60S Miners.

Source (primary)

Riot 8-K filed 2024-02-27 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Upon deployment of these new, more efficient and resilient Miners, Riot anticipates that the total hash rate capacity of its Rockdale Facility will increase from 12.4 EH/s to 15.1 EH/s by the end of July 2024.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Riot 8-K filed 2024-02-27

Quote: “Upon deployment of these new, more efficient and resilient Miners, Riot anticipates that the total hash rate capacity of its Rockdale Facility will increase from 12.4 EH/s to 15.1 EH/s by the end of July 2024.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed