jain.com

Rockdale 700 MW expansion completed

Company: Riot - Project: Rockdale

Subject kind
facility capacity
Statement date
2024-02-22
Promised amount
700.0 MW
Current status
stated

The claim, verbatim

Riot completed its 700 megawatt Rockdale Facility expansion.

Source (primary)

riot 8-K exhibit (riot-20240222xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-10)Live source ↗

Quote: “completion of our 700 megawatt Rockdale Facility expansion”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The CEO lists completion of the 700 megawatt Rockdale expansion among Riot's 2023 achievements.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000116741924000001/riot-20240222xex99d1.htm) in full (21,844 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms riot 8-K exhibit (riot-20240222xex99d1.htm)

Quote: “completion of our 700 megawatt Rockdale Facility expansion”

View cached copy (2026-11-10)Live source ↗