Morgan Stanley bridge facility maturity
Company: Riot - Project: Rockdale
The claim, verbatim
A Riot subsidiary has a delayed-draw facility of up to $573 million from Morgan Stanley to fund long-lead equipment for the 191 MW AI lab build at Rockdale. Under the August 10 Form 8-K, the loans mature on December 31, 2026, subject to the agreement's terms.
Source (primary)
Riot Platforms’ $573 Million Bridge Loan Comes Due December 31 as Shares Fall 8% in October’s First Week. Time to Sell or Load Up? - Yahoo Finance (-, news_article)
View cached copy (2026-10-09)Live source ↗
Quote: “Under the August 10 Form 8-K, loans mature on December 31, 2026, subject to the agreement's terms.”
How we checked this
Checked on October 14, 2026. The cited source supports every part of this claim.
The article states the lender, the amount, the purpose, and the December 31, 2026 maturity under the August 10 Form 8-K.
Confirmed in the source:
- A Riot subsidiary has a delayed-draw facility of up to $573 million
- The facility is from Morgan Stanley
- The facility funds long-lead equipment for the 191-megawatt AI lab build at Rockdale
- Under the August 10 Form 8-K, the loans mature on December 31, 2026, subject to the agreement's terms
What we did: Read our cached copy of the publisher (https://finance.yahoo.com/markets/stocks/articles/riot-platforms-573-million-bridge-130227491.html) in full (11,538 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Riot Platforms’ $573 Million Bridge Loan Comes Due December 31 as Shares Fall 8% in October’s First Week. Time to Sell or Load Up? - Yahoo Finance
Quote: “Under the August 10 Form 8-K, loans mature on December 31, 2026, subject to the agreement's terms.”
confirms Riot Platforms’ $573 Million Bridge Loan Comes Due December 31 as Shares Fall 8% in October’s First Week. Time to Sell or Load Up? - TIKR.com
Quote: “A Riot subsidiary has an up-to-$573 million delayed-draw facility from Morgan Stanley (MS). It funds long-lead equipment for the 191-megawatt AI lab build at Rockdale. Under the August 10 Form 8-K, loans mature on December 31, 2026”