Rockdale AI lab first 96 MW rent start

Company: Riot - Project: Rockdale

Subject kind
facility timeline
Statement date
2026-10-08
Promised by
2027-12-31
Promised amount
96.0 MW
Current status
stated

The claim, verbatim

Riot is targeting rent on the first 96 megawatts of the AI lab in December 2027.

Source (primary)

Riot Platforms’ $573 Million Bridge Loan Comes Due December 31 as Shares Fall 8% in October’s First Week. Time to Sell or Load Up? - Yahoo Finance (-, news_article)
View cached copy (2026-10-09)Live source ↗

Quote: “Riot is targeting rent on the first 96 megawatts in December 2027.”

How we checked this

Checked on October 14, 2026. The cited source supports every part of this claim.

The article states the December 2027 rent target for the first 96 megawatts, in its section on the AI lab bridge loan.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://finance.yahoo.com/markets/stocks/articles/riot-platforms-573-million-bridge-130227491.html) in full (11,538 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot Platforms’ $573 Million Bridge Loan Comes Due December 31 as Shares Fall 8% in October’s First Week. Time to Sell or Load Up? - Yahoo Finance

Quote: “Riot is targeting rent on the first 96 megawatts in December 2027.”

View cached copy (2026-10-09)Live source ↗

confirms Riot Platforms’ $573 Million Bridge Loan Comes Due December 31 as Shares Fall 8% in October’s First Week. Time to Sell or Load Up? - TIKR.com

Quote: “Riot is targeting rent on the first 96 megawatts in December 2027.”

View cached copy (2026-10-10)Live source ↗Archive.org ↗