jain.com

20-year frontier AI lab data center lease at Rockdale

Company: Riot - Project: Rockdale

Subject kind
customer
Statement date
2026-08-09
Promised by
2048-06-30
Promised amount
9100000000.0 USD
Current status
stated

The claim, verbatim

Executed 20-year lease with leading frontier AI lab for 191 MW critical IT capacity at Rockdale campus expected to generate approximately $9.1 billion in total initial contract revenue through June 2048

Source (primary)

riot 8-K exhibit (riot-20260810xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-01)Live source ↗

Quote: “Executed 20-year data center lease with a leading frontier AI lab for 191 MW of critical IT capacity at Riot's Rockdale campus, expected to generate approximately $9.1 billion in total contract revenue over the initial term”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms riot 8-K exhibit (riot-20260810xex99d1.htm)

Quote: “Executed 20-year data center lease with a leading frontier AI lab for 191 MW of critical IT capacity at Riot's Rockdale campus, expected to generate approximately $9.1 billion in total contract revenue over the initial term”