Fourth building at Rockdale Facility completion
Company: Riot - Project: Rockdale
What the later record shows
Delivered; the record does not say when
The claim says completing the fourth building would finalize the expansion, and a later filing states the expansion was finalized at 700 MW. Developed capacity rose from 630 MW (end-2022) to 700 MW (end-2023), but no passage dates the completion against Q1 2023.
“Developed power capacity (MW) (3) Rockdale Facility 700 700 630”
2025-02-27 · Riot 10-K filed 2025-02-28 View cached copy (2026-08-31)Live source ↗
“we have finalized our expansion and added approximately 400 MW to the Rockdale Facility, bringing its total developed capacity to 700 MW of electrical power”
2025-12-30 · Riot 424B5 filed 2025-12-31 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Fourth building at Rockdale Facility nearing completion in first quarter of 2023; when completed will finalize the Rockdale Facility expansion
Source (primary)
Riot 10-K filed 2023-03-02 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “a fourth is nearing completion in the first quarter of 2023, which, when completed, will finalize our Rockdale Facility expansion”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The 10-K says three new buildings were completed in 2022 and a fourth was nearing completion in Q1 2023, which would finalize the expansion.
Confirmed in the source:
- A fourth building at the Rockdale Facility was nearing completion in the first quarter of 2023
- Completing the fourth building will finalize the Rockdale Facility expansion
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000155837023002704/riot-20221231x10k.htm) in full (577,023 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Riot 10-K filed 2023-03-02
Quote: “a fourth is nearing completion in the first quarter of 2023, which, when completed, will finalize our Rockdale Facility expansion”
confirms Riot 10-K filed 2025-02-28
Quote: “Developed power capacity (MW) (3) Rockdale Facility 700 700 630”
confirms Riot 424B5 filed 2025-12-31
Quote: “we have finalized our expansion and added approximately 400 MW to the Rockdale Facility, bringing its total developed capacity to 700 MW of electrical power”
