Total contracted capacity at Rockdale campus

Company: Riot - Project: Rockdale

Subject kind
facility capacity
Statement date
2026-08-19
Promised amount
241.0 MW
Current status
stated

The claim, verbatim

AI lab and AMD leases together represent 241 MW of contracted critical IT capacity

Source (primary)

Foley Represents Riot Platforms on $9.1B AI Data Center Lease at Rockdale Campus - foley.com (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “Together, the two agreements represent 241 MW of contracted critical IT capacity”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Foley Represents Riot Platforms on $9.1B AI Data Center Lease at Rockdale Campus - foley.com

Quote: “Together, the two agreements represent 241 MW of contracted critical IT capacity”

View cached copy (2026-08-31)Live source ↗