AMD lease full 50 MW at Rockdale
Company: Riot
The claim, verbatim
The full 50 MW AMD lease is on track for May 2027, after the first 25 MW was commissioned and stabilized in May 2026.
Source (primary)
Riot Platforms Inc (RIOT) (Q3 2026) Earnings Call Highlights: $38 Billion in AI Data Center ... - Yahoo Finance (-, news_article)
View cached copy (2026-11-05)Live source ↗
Quote: “AMD Lease: 25 MW commissioned and stabilized in May 2026; full 50 MW on track for May 2027”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Riot Platforms Inc (RIOT) (Q3 2026) Earnings Call Highlights: $38 Billion in AI Data Center ... - Yahoo Finance
Quote: “AMD Lease: 25 MW commissioned and stabilized in May 2026; full 50 MW on track for May 2027”