Justified Data
Project of TeraWulf
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 480 MW | 2026-08-21 | Justified Data Campus 480 MW capacity |
| Contracted a customer is on the hook | 482 MW | 2026-08-31 | Kentucky power approval for Justified Data Campus |
| Under construction | 482 MW | 2026-08-24 | Kentucky data center power capacity |
| Permitted | 482 MW | 2026-08-24 | Justified Data Campus power capacity approved |
| Interconnect approved utility has agreed to deliver | 482 MW | 2026-08-31 | Justified Data Campus power capacity |
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 482 MW | 2026-08-24 | Justified Data Campus power capacity |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2026-05-26
Anthropic - anchor tenant · 401 MW · 20-year term source
Claims about this project
2026-02-01 - stated
2026-03-15 - stated
2026-04-13 - stated
2026-04-13 - stated
2026-04-13 - stated
Hawesville Site power availability 480.0 MW.
2026-04-14 - stated
2026-04-14 - stated
Hawesville Site power availability 480.0 MW.
2026-04-14 - stated
$500 million Bridge Credit Facility 500000000.0 USD.
2026-04-15 - stated
Hawesville Site power capacity 480.0 MW.
2026-04-15 - stated
Bridge credit facility 500000000.0 USD.
2026-04-15 - stated
2026-05-26 - stated
2026-08-14 - stated
2026-08-14 - stated
2026-08-21 - stated
2026-08-21 - stated
2026-08-21 - stated
Justified Data Campus 480 MW capacity 480.0 MW.
2026-08-24 - stated
2026-08-24 - stated
Authorized electric service capacity 482.0 MW.
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
Kentucky data center investment estimate 4.5 Billion USD.
2026-08-24 - stated
2026-08-24 - stated
482 MW secured for Justified data center 482.0 MW.
2026-08-24 - stated
Estimated $4.0-4.5 billion investment in Justified Data Campus development 4000.0 USD millions.
2026-08-24 - stated
2026-08-24 - stated
Expected capital investment in initial data halls and site development 4000000000.0 USD.
2026-08-24 - stated
Anthropic lease agreement and contracted revenue 19000000000.0 USD.
2026-08-24 - stated
2026-08-24 - stated
Justified Data Campus initial development investment estimate 4000000000.0 USD.
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
Anthropic 20-year lease for AI computing capacity 19000000000.0 USD.
2026-08-24 - stated
2026-08-24 - stated
Justified data center power capacity 482.0 MW.
2026-08-24 - stated
2026-08-24 - stated
Justified Data Campus power capacity 482.0 MW.
2026-08-24 - stated
Anthropic power supply customer 401.0 MW.
2026-08-24 - stated
Justified Data Campus Capital Investment Estimate 4.0 billion USD.
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
Kentucky data center power capacity 482.0 MW.
2026-08-24 - stated
Justified Data Campus power allocation 482.0 MW.
2026-08-24 - stated
2026-08-24 - stated
Site development and data halls investment at Justified Data Campus 4250000000.0 USD.
2026-08-24 - stated
2026-08-24 - stated
Justified Data Campus site development and data hall investment 4500000000.0 USD.
2026-08-24 - stated
Justified Data Campus power capacity 482.0 MW.
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
Anthropic 20-year lease at Justified Data Campus 19000.0 USD.
2026-08-24 - stated
Service delivery begins at Justified Data Campus. Promised by 2027-12-01.
2026-08-24 - stated
Campus reaches full power capacity. Promised by 2028-01-01.
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-25 - stated
2026-08-25 - stated
2026-08-25 - stated
Anthropic lease for 401 MW capacity 401.0 MW.
2026-08-25 - stated
2026-08-25 - stated
2026-08-25 - stated
Justified data campus power agreement 482.0 MW.
2026-08-25 - stated
Anthropic capacity lease at Justified 401.0 MW.
2026-08-25 - stated
2026-08-25 - stated
2026-08-25 - delayed
2026-08-25 - stated
2026-08-25 - stated
2026-08-25 - stated
Anthropic capacity lease at Justified 401.0 MW.
2026-08-25 - stated
2026-08-25 - stated
2026-08-25 - stated
Justified data center capacity approval 482.0 MW.
2026-08-25 - stated
401 MW leased to Anthropic at Justified 401.0 MW.
2026-08-25 - stated
2026-08-25 - stated
401 MW leased to Anthropic at Justified 401.0 MW.
2026-08-25 - stated
Anthropic contracted revenue 19000.0 USD.
2026-08-25 - stated
2026-08-25 - stated
2026-08-25 - stated
2026-08-25 - stated
2026-08-25 - stated
2026-08-26 - stated
Justified data-center campus development scale 4.5 billion USD.
2026-08-26 - stated
2026-08-26 - stated
2026-08-26 - stated
Justified data center development project 4.5 billion USD.
2026-08-27 - stated
Anthropic 20-year lease at Justified Data Campus 19000000000.0 USD.
2026-08-27 - stated
20-year Anthropic lease at Justified Data Campus 19000000000.0 USD.
2026-08-31 - stated
Anthropic hosting partnership 19000000000.0 USD.
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
2026-08-31 - stated
Justified Data Campus capital investment 4000000000.0 USD.
2026-08-31 - stated
Justified Data Campus power capacity 482.0 MW.
2026-08-31 - stated
HPC lease contract with Anthropic 19000000000.0 USD.
2026-08-31 - stated
2026-08-31 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-02 - stated
Anthropic data-center capacity 401.0 MW.
2026-09-02 - stated
20-year Anthropic data-center lease 19000000000.0 USD.