TeraWulf estimates $4 billion to $4.5 billion for site development and initial data halls, excluding Anthropic's computing equipment

Source (primary)

TeraWulf Advances $4B Data Center at Former Kentucky Smelter - Engineering News-Record (-, news_article)
View cached copy (2026-09-01)Live source ↗

Quote: “TeraWulf now estimates $4 billion to $4.5 billion for site development and initial data halls, excluding Anthropic's computing equipment and related infrastructure”

How we checked this

Checked on September 15, 2026. The cited source supports every part of this claim.

The article reports TeraWulf's current estimate of $4 billion to $4.5 billion, excluding Anthropic's computing equipment and related infrastructure.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.enr.com/articles/63556-terawulf-advances-4b-data-center-at-former-kentucky-smelter) in full (11,913 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf Advances $4B Data Center at Former Kentucky Smelter - Engineering News-Record

Quote: “TeraWulf now estimates $4 billion to $4.5 billion for site development and initial data halls, excluding Anthropic's computing equipment and related infrastructure”

View cached copy (2026-09-01)Live source ↗