jain.com

Anthropic 20-year data center lease

Company: TeraWulf - Project: Justified Data

Subject kind
customer
Statement date
2026-09-15
Promised by
2027-07-01
Promised amount
19000000000.0 USD
Current status
stated

The claim, verbatim

TeraWulf has a 20-year lease agreement with Anthropic for 401 MW at Justified Data Campus in Kentucky, valued at up to $19 billion of contracted revenue, with initial delivery scheduled for the second half of 2027

Source (primary)

TeraWulf Falls 5% as AI Infrastructure Names Extend a Month-Long Slide; IREN Drops 4%, Applied Digital Declines 3% - AOL.com (-, news_article)
View cached copy (2026-09-18)Live source ↗

Quote: “the 20-year Anthropic lease at Kentucky's Justified Data Campus for 401 MW, worth up to $19 billion of contracted revenue over the initial term...initial Anthropic delivery isn't scheduled until the second half of 2027”

How we checked this

Checked on September 24, 2026. The cited source supports every part of this claim.

The article states every element of the claim, although the two parts appear in separate sentences.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.aol.com/articles/terawulf-falls-5-ai-infrastructure-153049000.html) in full (9,722 characters, retrieved September 18, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf Falls 5% as AI Infrastructure Names Extend a Month-Long Slide; IREN Drops 4%, Applied Digital Declines 3% - AOL.com

Quote: “the 20-year Anthropic lease at Kentucky's Justified Data Campus for 401 MW, worth up to $19 billion of contracted revenue over the initial term...initial Anthropic delivery isn't scheduled until the second half of 2027”

View cached copy (2026-09-18)Live source ↗