Anthropic 20-year data center lease
Company: TeraWulf - Project: Justified Data
The claim, verbatim
TeraWulf has a 20-year lease agreement with Anthropic for 401 MW at Justified Data Campus in Kentucky, valued at up to $19 billion of contracted revenue, with initial delivery scheduled for the second half of 2027
Source (primary)
TeraWulf Falls 5% as AI Infrastructure Names Extend a Month-Long Slide; IREN Drops 4%, Applied Digital Declines 3% - AOL.com (-, news_article)
View cached copy (2026-09-18)Live source ↗
Quote: “the 20-year Anthropic lease at Kentucky's Justified Data Campus for 401 MW, worth up to $19 billion of contracted revenue over the initial term...initial Anthropic delivery isn't scheduled until the second half of 2027”
How we checked this
Checked on September 24, 2026. The cited source supports every part of this claim.
The article states every element of the claim, although the two parts appear in separate sentences.
Confirmed in the source:
- TeraWulf has a 20-year lease with Anthropic
- The lease covers 401 MW
- The site is the Justified Data Campus in Kentucky
- The lease is worth up to $19 billion of contracted revenue over the initial term
- Initial Anthropic delivery is scheduled for the second half of 2027
What we did: Read our cached copy of the publisher (https://www.aol.com/articles/terawulf-falls-5-ai-infrastructure-153049000.html) in full (9,722 characters, retrieved September 18, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf Falls 5% as AI Infrastructure Names Extend a Month-Long Slide; IREN Drops 4%, Applied Digital Declines 3% - AOL.com
Quote: “the 20-year Anthropic lease at Kentucky's Justified Data Campus for 401 MW, worth up to $19 billion of contracted revenue over the initial term...initial Anthropic delivery isn't scheduled until the second half of 2027”