Hawesville campus critical IT load of about 401 MW
Company: TeraWulf - Project: Justified Data
The claim, verbatim
The campus is expected to support about 401 megawatts of critical IT load.
Source (primary)
TeraWulf gets credit backstop from Google for Anthropic data-center project - WTVB (-, news_article)
View cached copy (2026-11-05)Live source ↗
Quote: “The campus is expected to support about 401 megawatts of critical IT load”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms TeraWulf gets credit backstop from Google for Anthropic data-center project - WTVB
Quote: “The campus is expected to support about 401 megawatts of critical IT load”
confirms TeraWulf gets credit backstop from Google for Anthropic data-center project - CNA
Quote: “The campus is expected to support about 401 megawatts of critical IT load”